Lake Oconee Boat Dock: New Double-Slip Aluminum Dock in Eatonton, GA
A returning customer in Eatonton was ready to retire an aging wood dock. We removed it, built a double-slip aluminum dock with Slate Gray PVC decking in its place, and reset their pontoon and PWC lifts.
Lifetime frame warrantyThe short version
Marine Specialties replaced an aging wood dock on Lake Oconee in Eatonton, GA with a double-slip aluminum dock on 3″ galvanized steel piles, finished in TimberTech cellular PVC decking. We handled the Georgia Power and Putnam County permits, removed and disposed of the old dock, and reinstalled the homeowners’ existing boat lifts. The frame and decking both carry lifetime warranties, and the decking adds a 50-year fade warranty.
Double-Slip Aluminum Dock, PVC Decking & Lift Reset
Everything below was part of one project, start to finish.
- Removal and disposal of the existing wood dock
- Double-slip aluminum dock with an open deck (no roof)
- 10″ aluminum C-channel dock frame
- 3″ Schedule 40 galvanized steel piles
- Aluminum stringers at 16″ on center
- TimberTech 100% cellular PVC decking in Slate Gray with stainless steel screws
- Soft-edge bumper package with 9 corner bumpers
- Retractable cleats
- 5-step angled swim ladder and a large dock box with gas struts
- Existing pontoon and PWC lifts removed and reinstalled
- Georgia Power permit plus Putnam County permit and inspection
From Wood Platform to Double-Slip Dock
Before
AfterTap the photo or use the buttons to switch views.
The Challenge
The wood dock had reached the end of its useful life. Replacing it took more than a new deck:
- Full removal first. The old dock had to come out and be hauled away before the new piles went in.
- Lifts already in the water. The pontoon lift and PWC lift had to be pulled and then reset at the new dock.
- Two permits. Lake Oconee docks need Georgia Power approval, and Putnam County requires its own permit and inspection.
- Access by water. Heavy materials came in by barge.
What Went Into This Dock
Specs from the dock package installed on this project.
The Build, Step by Step
One crew handled the project from permits to the last cleat. Select a step to see it.

Step 1: Permits & planning
We pulled the Georgia Power permit and the Putnam County permit, and scheduled the county inspection, so the build could start on a clean slate.

Step 2: Removal
The crew took out the old wood dock and hauled it away, then pulled the existing pontoon and PWC lifts so they could be reset later.

Step 3: Frame built on shore
We assembled the 10″ aluminum C-channel frame sections on shore, with stringers at 16″ on center.

Step 4: Piles & frame set
3″ Schedule 40 galvanized steel piles went in, and the frame was set on them to form the two boat slips.

Step 5: Decking
TimberTech cellular PVC decking in Slate Gray went down with stainless steel screws. There is nothing to stain or seal.

Step 6: Finish & lifts
We added the soft-edge bumpers, 9 corner bumpers, retractable cleats, swim ladder and dock box, then reinstalled both lifts at the new dock.
More From This Project
Select any photo to see it full size. Use the arrows or swipe to browse.
The Result
- Room for both boats. Two slips, with the pontoon lift and PWC lift back in service.
- Nothing to stain or seal. Aluminum framing and cellular PVC decking replace wood that needed regular upkeep.
- Covered for the long haul. Lifetime frame warranty, lifetime decking warranty and a 50-year fade warranty.
- Permitted and inspected. Georgia Power and Putnam County approvals handled by our team.
Planning a new dock? See our custom boat dock systems and Lake Oconee dock services, or browse more finished work on our project map.
Lake Oconee Dock FAQ
Do I need a permit to build a dock on Lake Oconee?
Yes. Lake Oconee docks need a shoreline permit from Georgia Power, and your county may require its own building permit and inspection. On this Eatonton project, we handled the Georgia Power permit and the Putnam County permit and inspection.
How long does it take to replace a dock?
This one took 8 working days on site, from removing the old wood dock to reinstalling the lifts. Timing for your dock depends on its size, the permit schedule and whether lifts need to be moved.
Why choose aluminum and PVC over wood?
An aluminum frame won’t rot, and cellular PVC decking doesn’t need staining or sealing. On this dock, the frame carries a lifetime warranty and the TimberTech decking carries a lifetime warranty plus a 50-year fade warranty.
Can you keep my existing boat lifts?
Yes, if they’re in good condition. On this project, removing and reinstalling the homeowners’ pontoon and PWC lifts was part of the dock package.
Get a Free Dock Estimate on Lake Oconee
Tell us about your shoreline and your boats. Our Eatonton office serves Lake Oconee and Lake Sinclair.
- Marine construction since 1988
- Licensed & insured
- Permits handled for you
- Free design consultations